Safety Precautions
- A work permit must be issued and the qualified maintenance staff should carry the suitable safety category,
- Safety fence (rope) with caution marks surrounding the work area,
- Transformer isolation and proper grounding is rquired
- Wear your safety helmet
Tools and Equipment
- Complete tool set
- Digital DC voltmeter
- Blower or vacuume cleaner
- PVC ladder, brushes, megger 5000v/9000 vdc
Work to be Carried Out
- Check oil leaks,
- Check oil level in main tank, and bushings,
- Read and record the max oil temperature,
- Read and record the max winding temperature,
- Check all cooling fans for correct operation, and unusual noises,
- Check the transformer control cabinet for door seal, clean by blower with moderate pressure.
- Check the tap changer control cabinet ( if any ) for door seal, clean by blower with moderate pressure.
- Check the Silicagel breather,
- Clean all porcelain surfaces of all bushings insulators,
- Clean the neutral current transformer,
- Clean the neutral earth disconnect switch blades,
- Lubricate the neutral earth disconnected switch bearing points,
- Check all bolted connections for tightness,
- Measure the insulation resistance for each winding to ground to other winding and for core to ground
- Measure the winding turns ratio. R60/R15 > 1.2 every year
- Measure the winding resistance using megger 5000/9000 Vdc every year
- Check the pressure relief device,
- Check the temperature gauges indicator,
- Check all protection devices,
- Read and record the leakage current monitor test on the lightening arrestor,
- Check the Deluge system, transformer protection by water spray.
- Measure the insulation oil breakdown voltage test. every year.
- Operate the tap changer from up to down off load (in case of step down transformer) and change the oil every year in case of the transformer works at full load and every 2 years if at half load.
- Check the gas in the oil and treatment if necessary taking an oil sample
- As required perform Power Transformer tests
Maintenance Record Data Sheet
Works to be Carried out
|
Test Result
|
Any oil leaks (if yes give location) | Yes No |
Oil level in main tank | OK low add |
Oil level in bushings | OK low add |
Max oil temperature | oC |
Max winding temperature | oC |
All cooling fans operational (if "on" indicate no. of fan) | Yes No |
Cooling fans noise (if "yes" indicate no. of fan) | Yes No |
Transformer control cabinet cleaned and inspected | OK |
Tap changer control cabinet cleaned and inspected | OK |
Silicagel breather | OK Change |
All porcelain surfaces of all bushings insulators cleaned | OK |
Neutral earth disconnect switch blades cleaned | OK |
Neutral earth disconnected switch bearing points lubricated | OK |
Neutral CT cleaned | OK |
All bolted connections checked for tightness | OK |
Insulating oil breakdown voltage test average kv every year |
kv, air gap mm
|
Turns ratio value for winding R60/R15 > 1.2 every year
| OK Not |
Winding resistance using megger 5000/9000 Vdc every year | OK Not |
Pressure relief device, | OK Not |
Temperature gauges indicator | OK Not |
Record the leakage current monitor test on the lightening arrestor | |
(Deluge system) transformer protection by water spray | Yes No |
Check the tap changer (if any in case of step down transformer) and change the oil every year | OK Not |
Take oil sample for gas analysis and treatment if necessary
| OK Not |