⚡ Welcome to Substation Blog — Your resource for electrical engineering, safety & substation technology. About Us

Tuesday, 9 January 2018

Replacing a Long Section of Damaged Conductor in transmission line

 •   •  No comments
Introduction
The purpose of this procedure is to provide detailed instructions on a safe method for replacing a Long section of Damaged Conductor.
Safety Precautions
  • Obtain a work permit.
  • Use approved fall protection equipment and procedures.
  • Use approved earthing equipment and procedures.
  • Calculate the weight of the conductor at the suspension point and the line tension of the conductor in order to select the proper tools required to complete the work procedure safely.
  • Before beginning any work, check for other energized circuits beside, below or in the vicinity of the conductor that you will lower to the ground.
Tools and Equipment
3 Handlines
1 Complete Fall Arrest Equipment, 1 Rope Ladder
1 Complete Temporary Earthing Equipment
1 Wire Rope Cable fitted with conductor clamps on both ends
1 Tirfor Hoist,
1 Bulldozer or Bulldozer Winch or Large Truck
3 Snatch Blocks, 1 Hydraulic Press and Dies
1 Nylon Sling, 2 Conductor Grips
4 Steel Slings, 6 Shackles
1 Ratchet Cutters, 1 Steel Conductor Brush
1 Aluminum Cutters / Trimmers
2 Aluminum Sleeves, 1 Measuring Ruler
1 Potential Indicator, 2 Steel Sleeves
2 Bandage Ties or Tape

Work to be Carried Out
  1. Obtain a work permit on both circuits of the tower that you will work on.
  2. Climb the towers, using approved fall protection, where temporary earths will be installed taking care to maintain the minimum limits of approach to the conductor.
  3. Install the hand-line on the tower and raise the potential indicator.
  4. Verify the isolation of both circuits on the tower.
  5. Install temporary working earths on the circuit that you will be working on at the locations as shown in (FIGURE # 1) to ensure that the conductor will be properly earthed on both sides of the work location tower.
Figure 1: TEMPORARY TOWER EARTH LOCATIONS
6.     Climb the work location tower using approved fall arrest procedures and install a handline in an appropriate position.
7.     Install a rope ladder at the end of the arm that suspends the damaged conductor.
8.     Install 3 snatch blocks at the following locations as shown in (Figure # 2)
# 1 at the tower leg nearest the footing and diagonal member.
# 2 on the tower shaft at the arm connection.
# 3 at the end of the tower arm directly above the suspension clamp.

Figure 2
9.     Install the wire rope cable through the snatch blocks as shown in Figure 2.
10. As one lineman holds the weight of the cable on the tower arm, another lineman descends the rope ladder and attaches the free end of the wire rope cable to the conductor by using a nylon sling and shackle as a choker.
11. Attach the other end of the wire rope cable to the bulldozer, bulldozer winch or heavy truck.
12. Take up tension on the wire rope cable by advancing the vehicle or the winch until the suspension insulators hang slack.
13. The lineman on the rope ladder then disconnects the suspension clamp from the bottom insulator or insulator rod.
14. The conductor is then lowered to the ground gradually.
NOTE: If the conductor that is being lowered must pass by another tower arm and conductor, a tag line should be attached to the conductor to pull it by the arm by applying horizontal tension until it is clear. Also note that if the conductor that is being lowered to the ground is any other than the bottom phase conductor that it may have to be lowered from two tower locations in order to reach the ground for repair. These procedures must be anticipated prior to installing the temporary earth locations.
15. Measure the distance of the damaged conductor and mark the cutting points with tape.
16. Measure and cut the new conductor section to the exact same length.
17. Install two conductor grips and the tirfor hoist on the conductor outside of the cutting marks by approximately two meters to allow for cleaning and sleeving.
18. Take up tension on the tirfor hoist until the damaged conductor section between the two grips becomes slack.
19. Before cutting the damaged conductor section, temporary earthing jumpers must be installed across the entire conductor section to ensure that no induced potential voltage or current arises between two open points.
20. Please refer to (FIGURE # 4) two alternative methods of applying an earthing jumper cable across this section. Depending on the length of the damaged section to be replaced, the choice of either method is acceptable.




21. After either earthing jumper method has been applied and checked for continuity, prepare to cut the damaged conductor by applying a tape bandage approximately 1.5 meters outside of the cutting marks to prevent the existing conductor from unraveling. Cut the damaged conductor at the cutting marks and remove the damaged section.
22. Slide the aluminum sleeve on both ends of the new conductor section.
23. Clean the aluminum strands of all 4 conductor ends with emery paper.
24. Measure and mark the distance to cut the aluminum strands to expose the steel strands by a distance equal to half the length of the steel sleeve plus 5 % of the entire steel sleeve length. This will allow for steel expansion while pressing. (See Figure 5A).

 
25. Wrap a tape bandage around both ends of the steel strands and slide the steel strands inside the steel sleeve. Remove the tape bandage and insert the steel strands fully into the steel sleeve until both conductor ends meet in the center of the sleeve. See (Figure 5 B

 

 
26. Using the hydraulic press, begin pressing the steel sleeve from the middle towards each end and overlap each press by 10 %. SEE (Figure 6) and (Figure 7)

.
27. Cover the pressed steel sleeve with a coating of conductive grease such as Penetrox to prevent corrosion
.

 

 
28. Measure the length of the aluminum sleeve and mark the conductor on both sides of the steel sleeve to ensure that the aluminum sleeve will be centered appropriately over the steel sleeve.
29. Slide the aluminum sleeve over the conductor to line up with each mark accordingly.
30. Using the hydraulic press, begin pressing the aluminum sleeve by centering the die over the filler hole and outward to the end of the aluminum sleeve. Overlap each press by 10 %

  
31. When the aluminum sleeve has been completely pressed, fill the sleeve cavity with conductive grease as shown in (FIGURE # 8).
32. Gradually release the tirfor hoist to transfer the tension to the new conductor line section.
33. Remove the tirfoe hoist and grip assembly.
34. Remove the temporary earth jumper or jumpers from the repaired conductor section.
35. Raise the repaired conductor section using the winch or vehicle.
36. Attach the suspension clamp to the insulator string.
37. Release the wire rope cable from the conductor and lower it to the ground on the hand-line.
38. Remove the snatch blocks and rope ladder and lower them to the ground on the hand-line.
39. Advise the crew that the temporary earths on the adjacent towers will be removed.
40. Remove the temporary earths on the adjacent towers and lower them to the ground on the hand-line.
41. Descend the towers using approved fall arrest and remove the fall arrest equipment from the towers.
42. Close the work permit.


Power Transformer Oil Insulation Deterioration

 •   •  1 comment
Wildterra INT
Monitor the condition of insulating oil is a proactive means of detecting equipment problems in the early stages. However insulating oil can begin to deteriorate through relatively normal operating conditions and become a potential hazard to the proper operation of equipment.
This bulletin outline 4 common tests which are used to determine the degree of deterioration of insulating oil. These tests are Dielectric strength, neutralization number (acidity), resistivety and water content. The following section provides information regarding the IEC recommended values for each test and recommended test frequencies.
Information
Dielectric Strength Testing
The absorption of moisture by transformer insulating oil has a direct bearing on the transformer's insulation performance. Moisture content is normally checked by measuring the dielectric strength. It can also be checked by measuring an oil sample's resistively, tan 8, or actual water content.
The measurement of dielectric strength should be made with an oil tester rated according to the oil to be measured and using IEC electrodes. The following table provides the allowable KV ratings for dielectric testing. The frequency recommended for these tests by the IEC are as follows:
            - After filling or refilling,
            - Prior to energizing,
            - Then after 12 months and subsequently every 2 years after that,
            - Tap changer neutral point every 6 years.
Category of Transformer
Limits
> 420 Kv
> 50 Kv/2.5 mm
> 170 Kv up to 420 Kv
> 50 Kv/2.5 mm
> 72.5 Kv up to 170Kv
> 40 Kv/2.5 mm
Up to 72.5 Kv
> 30 Kv/2.5 mm
Neutral point of tapchanger
> 25 Kv/2.5 mm

Neutralization number (Acidity) Testing
The neutralization number is important because the level of acidity in the oil determines the rate of sludge buildup, -and sludge hinders cooling efficiency. Less than 0.2 inhibits sludge formation, 0.5 allows sludge buildup, and more than 0.5 accelerates sludge development.
According to IEC; for all transformers the neutralization number must not be greater than 0.5 mg Koh/g, at this point the oil would have to be processed. The frequency for this test is every 6 years as long as the test results do not exceed 0.3 mg Koh/g. Readings above this amount indicate the oil must be monitored closer and tested more often. The table below is an example taken from a Hitachi transformer manual and follows the guide set by IEC.
Neutralization number
Evaluation
less than 0.2
Good
0.2 to 0.5
Acceptable, but oil should be replaced soon
More than 0.5
Bad. Oil should be replaced immediately
Resistivity Testing
The resistively of the insulating oil is directly related to the insulation performance of the transformer. Resistively, such as insulation resistance, decreases with transformer temperature.
IEC recommends the following frequencies for conducting resistivity tests:
  • After filling and refilling,
  • Prior to energizing,
  • Then after 12 months and subsequently every 6 years after that.
The following table provides the IEC acceptable limit for resistivity  
Category Of Transformer
Limits Ohms-cm
20 degree C
90 degrees C
420 Kv
> 2 x 10 13
> 1 x 10 11
170Kv up to 420Kv
> 2 x 10 13
> 1 x 10 11
72.5Kv up to 170Kv
> 6 x 10 12
> 2 x 10 11
Testing For Water Content
            Measure the water content of the oil by using the Karl Fischer method
  • Note: The Karl Fischer method detects the existence of water in the organic solvent. It calls for titration of the sample liquid by dissolving the sample oil in absolute methyl alcohol, then introducing the dissolved sample by measured amounts into the Karl Fischer reagent, which is a solution of iodine, sulfur dioxide, pyridine, and absolute methyl alcohol with a reddish brown color. The color of the reagent becomes light yellow if water exists in the sample liquid. The end point is found visually or by potentiometric titration.
The table below provides the IEC limits for water content which are only applicable where the acidity values are > 0.1 mg KOH/g.

Category Of Transformer
Limits
Frequency of Tests
> 420 Kv
> 170 Kv up to 420 Kv
< 20 mg/Kg
  • After filling or refilling,
  • Prior to energizing,
  • Then after 12 months, subsequently in conjunction with dissolved gas analysis testing.
> 72.5 Kv up to 170 Kv
< 20 mg/Kg
  • After filling or refilling,
  • Prior to energizing,
  • Then after 12 months, subsequently every 6 years or in conjunction with dissolved gas analysis testing.
Up to 72.5 Kv
No free moisture at room temperature
Only when breakdown voltage approaches the rejection level.


Codes and standards for Substation Battey banks installation and practices

 •   •  No comments


IEEE 450
Recommended Practice for Maintenance, Testing, and Replacement of Vented Lead Acid Batteries for Stationary
Appliactions.

IEEE 484
.

Recommended Practice for Installation Design & Installation of Vented Lead Acid Storage Batteries for Stationary
Applications
IEEE 1106
Recommended Practice for Installation, Maintenance Testing
& Replacement of Vented Nickel-Cadmium Batteries for
Stationary Applications
IEEE 1187
Recommended Practice for Installation Design & Installation
of Valve-Regulated Lead-Acid Storage Batteries for Stationary

IEEE 1188
Recommended Practice for Maintenance Testing &
Replacement of Valve-Regulated Lead-Acid Batteries for
Stationary Applications.

IEC 61438
Possible Safety and Health Hazards in the Use of Alkaline
Secondary Cells and Batteries.

NESC/ANSI C2
National Electrical Safety Code
NFPA 70

National Electrical Code


Featured Post

The necessary response to substation problems

  When it comes to power distribution, substations are the backbone of our grid. Keeping them in optimal condition is essential to ensure re...

Popular Posts